Important Points
1. The submission of Solar PV Equipment enrollment applications shall be done through the DRRG Equipment Portal. For any enquiries or support related to the solar PV equipment enrollment, send email to pvequipment@dewa.gov.ae
2. The equipment that meets the minimum eligibility criteria will be added in the List of Eligible Equipment. This list is periodically updated.
3. The mandatory compliance certificates shall be issued from 3rd party ILAC-accredited labs according to the standard ISO/IEC 17025.
Note the old PDF list of Eligible Equipment is obsolete and shall not be consider for solar installations.
In line with Dubai’s vision to become a global hub for green economy, DEWA has launched the Distributed Renewable Resources Generation programme to encourage customers to adopt solar energy as a mean of producing their own electricity. Surplus production will be fed into DEWA’s power network while the owner will be credited for off-setting future use.
DEWA has committed to maintain high technical standards for these installations. Therefore, the solar PV equipment to be installed will undergo a rigorous process of verification to ensure compliance with the eligibility criteria set by DEWA based on international standards on quality and safety, as described in the following document:
DEWA Standards for Distributed Renewable Resources Generators.
In this document, please refer to:
Appendix C: List of Standards for Equipment:
C.2 PV modules.
C.3 Inverters.
Appendix D: Compliance Tests:
D.1 Interface Protection Systems for Low Voltage Connected RRGPs.
D.2 Interface Protection Systems for Medium Voltage Connected RRGPs.
D.3 Inverters for Low Voltage Connected RRGPs.
D.4 Inverters for Medium Voltage Connected RRGPs.
Minimum Eligibility Criteria (Please refer to the standards document in the "PV Equipment Eligibility Overview" section for details):
PV Modules: The minimum eligibility of the PV module depends on the compliance to the following standards:
(Detailed guide available here)
PV Inverters: The minimum eligibility of the PV Inverter depends on the compliance to the following standards:
(Detailed guide available here)
Please note that addit